Project + Liza Unity FPSO
Keppel Shipyard, Singapore

About the project

Powertech has carried out termination and testing of the HV cable systems as well as the high & low voltage protection testing works for SBM Singapore.

The work we have successfully completed include;

  • HV Cable Termination and VLF Testing
  • 1C x 185mm2 – 27 lengths
  • 1C x 300mm2 – 60 lengths
  • 3C x 50mm2 – 26 lengths
  • 3C x 150mm2 – 8 lengths
  • LV Switchboard
  • MV Switchboard
  • ABB Protection relays with 61850 and Goose programming
  • ClientSBM, Singapore
  • Start Date2020
  • End Date2021