Project + South Flank
Pilbara, WA

About the project

Powertech provided a large scale multidiscipline commissioning team to support the commissioning activities on BHPs newly constructed South Flank Iron Ore mine.

The Powertech teams work scope included all aspects of commissioning including, planning, documentation, engineering support, as well as hands on commissioning activities. At peak Powertech had over 150 personnel on site.

  • High Voltage Substation FAT & SAT
  • Non-Process Facilities Commissioning
  • Processing Plant Commissioning
  • Instrumentation Loop & Function testing
  • Control System testing
  • Punchlist and rectification works
  • Motor and pump alignments
  • Commissioning of Utility systems
  • Conveyor System Commissioning
  • Stacker commissioning
  • Reclaimer Commissioning
  • Crusher Commissioning
  • ClientBHP
  • Start Date2019
  • End DateOngoing